Cement industry projects
Adana Cement Industry - Klinger mill installation project 133 Ton/ h.

2008 ADANA CEMENT CO. - ISKENDERUN

 

133 Ton/h. Scal and Klinger Mill Poroject.

In this project scope, basically the following equipments have been fabricated and erected; one LOESCHE mill ( capacity of 133 Ton/h ), one SCHEUCH bag filter ( capacity is 560.000 m3/h.),two pieces of SIMGE bag filter ( 5000 and 9000 m3/h.), two pieces of silos ( capacity 30 m3) 3 pieces of belt conveyying systems, one AUMUND elevator ( capacity 35 Ton/h.), 3 pieces of BEUMER elevators ( capacity 203 Ton/h.), fabrication and installation of 200 ton gas ducting.

Engineering : LOESCHE / ERENCO / SIMGE

Main Contractor : ERENCO A.S

Sub Contravtor   : SIMGE Co. LTD.

Controlled by     : ERENCO A.S